Mercury Vapor
Lamp Tester
The final testing of large base mercury vapor lamps requires light
up and seasoning of the product for eight minutes.
After the eight minute run, the lamp is inspected for power consumed
which is an indicator of the lamps quality and expected life. Traditionally
lamps were bulk packed and moved to an off line area where they
were batch tested. MRI designed and built a continuous testing machine
that permitted testing at the end of the line matching the upstream
production rate of 1200 lamps per hour.
The
tester eliminated the bulk storage WIP as well as eliminating the
overtime associated with the capacity limiting traditional testing
methods. Electronic data logging provided statistical information
for the corporate Six-Sigma initiative of this major manufacturer
of lighting products.
|